Research

Bringing the Heat to CHE

February 01, 2016
For about 10 years, the cage washer at the Center for Health and the Environment (CHE) wasn’t getting the steady, continuous flow of steam needed to quickly heat water to 180 degrees Fahrenheit – the state mandated temp for sterilizing their research equipment.

New Pipes for Tupper

December 01, 2015
Back in 1970, when Tupper Hall opened, Tyler hub and spigot cast iron pipe had been the standard drainpipe for over 40 years. Thousands of feet of the stuff zig-zagged throughout the building.

Center for Neuroscience Now a Whole Lot Cooler

September 01, 2015
Building Maintenance Services made great use of some deferred maintenance funding when our Mechanical HVAC shop completed its installation of 11 air handling units (AHU) at the Center for Neuroscience in late July.